This job had to be completed out with a very short window of time – after the football season ended and before the pre-season training began, leaving only a 5 week period in which we had access to carry out the job.
Newcastle United Football Club
The East Coast Mainline runs adjacent to this NUFC training facility and the client had encountered trespass issues, with young kids trying to get close to watch the team training.
Three days of devegetation works were carried out to remove overhanging limbs and sidings. Wire fencing with 1.2m concrete posts were removed and 412m of 1.8m high GPC Expamet fencing was
installed in its place.
Netting was also installed to stop rabbit from breaking through and getting onto the pitch, which had previously been an issue causing damage.