QTS was awarded this remit to install 1300 yards of crest ditch to catch all surface water for third party land and divert away from the large embankments of the DCL line.
Hatton Crest
The QTS team was mobilised to first clear 5,000 sq/yards of vegetation. Hand tools and tracked chippers were utilised to create a path for the excavators to install the crest drainage.
All chippings and spoil never left site, with all being landscaped into the existing area. All work was carried out safely with no accidents and incidents throughout this project. QTS used inhouse trained personnel and QTS specialist plant and equipment, working in partnership with Network Rail